The North Road Is Getting Pavement and Secret Beach Is Getting Power. Only One Has a Timeline.

October 22, 2026

Two Secret Beach announcements came out on October 15. If you drive north from the Sir Barry Bowen Bridge this winter, which one will you actually notice?

Mostly the road. The San Pedro Town Council is paving about six miles between the Belizean Shores area and Secret Beach, ending near Roadkill Bar, and expects the job to take about seven months, weather permitting. On the same day, Belize Electricity Limited and the Belize Tourism Board said they will connect Secret Beach to the national grid. Ambergris Today reported that the announcement included no project cost and no completion date. The two projects got announced together, and they'll probably get talked about together. But one is a work crew with an estimate, and the other is a commitment with no date attached.

Two announcements, side by side

North road paving Secret Beach grid connection
Who San Pedro Town Council BEL and the Belize Tourism Board
Scope About six miles, Belizean Shores area to Secret Beach near Roadkill Bar Extension of the national grid to Secret Beach
Stated timeline About seven months, depending on weather None given
Stated cost Not reported None given
Work described Grading, fill, paving, drainage, speed bumps Coordination with residents and businesses as work begins

The paving column comes from the Council's Operations Manager, Alex Ek, who gave an update on October 14 that the San Pedro Sun published the next day. The power column comes from a joint BEL and BTB press release. It describes a targeted grid extension for residents, business owners and visitors, but it doesn't lay out phases, a line route, or which properties will be connected. 7 News Belize also reported that no timeline was given.

So a resident has one date to plan around, and even that one comes with a weather condition attached.

Why the seven months depends on the weather

Count seven months from mid-October and you land around mid-May 2027, assuming the estimate holds. The Council's own reporting on the north road over the past year explains why that's a big assumption.

Here's the north road's recent history, as the San Pedro Sun has covered it:

  1. December 4, 2025. Council crews had graded, spread reef rock and compacted road sections starting just past Belizean Shores, including the stretch from Blue Dolphin through the Secret Beach junction.
  2. January 31, 2026. Ek said the northern roads had been graded and repaired in December, but rain since then had reversed some of that progress, so crews went back with rollers and road markings. In the same update, he blamed the deterioration on cold fronts, heavy rain and construction traffic, especially on the northern sand roads.
  3. March 7, 2026. Crews were preparing road bases on the northern stretch from Coco Beach Resort toward Secret Beach, and paving further north was described as a longer-term plan.
  4. October 15, 2026. The Council announced the paving push to Roadkill Bar. Ek said some sections are in worse shape than others and will need repairs before paving can start.

The pattern is clear in the Council's own words. Ground gets prepared in the dry stretch, the rain undoes some of it, and the crews go back over it. The October report repeats the caveat itself, saying heavy rain could hold up grading, filling, drainage and paving. The weeks of cold fronts that wore down the road last winter fall right in the middle of this project's estimate.

Some of that history is also progress. The reef rock base laid between Belizean Shores, Blue Dolphin and the Secret Beach junction was meant to firm up the road ahead of permanent paving, according to the Council. This round builds on that earlier groundwork.

What the drive north looks like while crews work

The work plan covers more than asphalt. Crews will grade, fill and pave the remaining sections, put in drainage to carry water away from the road and nearby properties during heavy rain, and add speed bumps along stretches shared by golf carts, other vehicles, pedestrians and cyclists. The Council expects the finished route to give a continuous paved drive from the Sir Barry Bowen Bridge to Secret Beach.

The drainage matters as much as the pavement. The San Pedro Sun's report says standing water and crumbling surfaces have made parts of the route hard to drive, especially in rainy periods. Pavement without drainage would face the same water that kept washing out the graded base last winter.

While the work goes on, Ek has asked drivers to follow traffic rules, be patient, and take care around crews and unfinished sections. In practice, a golf cart trip to the beach this season means passing active crews, and the time it takes will depend on which sections are being rebuilt that week.

Closer to town, the north side keeps gaining places worth stopping at. Larimar Seafood and Steakhouse opened May 23 in Tres Cocos, in the space that used to be Sweet Basil and Legends Burger House, and the San Pedro Sun reported dinner service Wednesday through Monday.

The power line has a purpose but no calendar

The grid announcement is more about intentions than logistics. In BEL and BTB's description, Secret Beach businesses currently depend on fuel-powered generators. The agencies expect a grid connection to cut operating costs, shrink the environmental footprint of businesses there, and improve public and commercial lighting. Love FM's report put it more specifically, citing less generator noise and fewer emissions, and raised the possibility that businesses could stay open later once they're off generators. Ambergris Today described the lighting improvement as something that would help restaurants safely extend their evening hours.

These are goals the agencies have stated, and they're the right ones for this part of the island. Better lighting, quieter nights and later dinner service would change how Secret Beach feels after sunset. But no one has said when any of it will happen, which properties come first, or how the line will run north. The agencies have said they'll work with community stakeholders and local businesses once implementation starts. That's where a timeline is most likely to show up.

The two projects also connect physically. Ambergris Today ran a photo caption with its power story noting that the long, bumpy roads to Secret Beach are slowly being paved. Utility work and road work along the same corridor have to be coordinated somehow. Neither announcement says how.

Why both answers trace back to one meeting in August

Neither project came out of nowhere. On August 7, Secret Beach stakeholders met to go over problems in the area, and the San Pedro Sun's account records Secret Beach Association leaders saying that development was outpacing infrastructure and that the access road needed work. Garbage collection and public health came up at the same meeting, and the Council's representative couldn't give a timeline for a garbage plan.

Ten weeks later, the October 15 road report gave the clearest answer yet to the access-road concern. The power announcement responded to the generator problem in principle. Garbage, the third item on the August list, wasn't part of either announcement. So the infrastructure that was supposed to catch up with growth is arriving in three different states: one item has a schedule, one has a promise, and one is still waiting on a plan.

That's what's useful to know heading into high season. The road work is real and underway, and the rain will decide how fast it moves. The grid connection is official but has no date, so anything on the north side that depends on grid power has nothing yet to plan around. Updates from the Council or from BEL and BTB on the stakeholder process will be the first real sign of when Secret Beach evenings start to change.

For owners on North Ambergris Caye, access and utilities shape both the commute and how a property gets used and looked after when you're away. At New Dawn Realty, our property management team keeps an eye on north-road conditions and utility updates so absentee owners get a plain account of what's changing near their property. If you'd like help understanding how the paving work or a future grid connection affects your plans up north, start your Belize property search with us.